Site Visit 20171101
Nov 01, 2017   

1.Culture & Sport Center 
1st floor structure completed
2nd floor formwork 80%,rebar 70%, concreting 50%

2.Classroom Building
Ground floor structure completed
1st floor structure completed
2nd floor structure completed
3rd floor formwork 75%, rebar 50%, concreting 25%
4th floor formwork 25%, rebar 25%, concreting 25%                                                                                                                                                                                                                                                                                                   

3.Dormitory
Ground floor concreting 100%
1st floor formwork 90%, rebar 60%, concreting 50%

4.Podium & Activity Center
Ground floor concreting 100% 
1st floor formwork 100%, rebar 80%, concreting 60%